Tentative Environmental Monitoring Schedule between 29-January 2006and 28-February 2006
Sunday   Monday    Tuesday   Wednesday   Thursday   Friday   Saturday  
  29-Jan   30-Jan   31-Jan   1-Feb   2-Feb   3-Feb   4-Feb
            24hrs-TSP 1hr-TSP          
              Noise          
              NoiseEvening    
                NoiseNight        
  5-Feb   6-Feb   7-Feb   8-Feb   9-Feb   10-Feb   11-Feb
NoisePH       24hrs-TSP 1hr-TSP              
        Noise            
        NoiseEvening      
            NoiseNight            
  12-Feb   13-Feb   14-Feb   15-Feb   16-Feb   17-Feb   18-Feb
NoisePH   24hrs-TSP 1hr-TSP               24hrs-TSP
      Noise              
      NoiseEvening        
        NoiseNight                
  19-Feb   20-Feb   21-Feb   22-Feb   23-Feb   24-Feb   25-Feb
NoisePH   1hr-TSP               24hrs-TSP 1hr-TSP  
    Noise              
    NoiseEvening          
    NoiseNight                    
  26-Feb   27-Feb   28-Feb                
NoisePH                          
                   
               
                           
1hr-TSP  3 x 1 hour TSP monitoring at ASR1, ASR2 and ASR3 during 09:00~18:00.
24hrs-TSP 24 hours TSP monitoring at ASR1, ASR2 and ASR3
Noise Leq30 measurement at NSR1, NSR2 and NSR3 during 07:00~19:00.
NoiseEvening 6 x Leq5 will be measured at NSR1, NSR2 and NSR3 during 19:00~23:00 (if construction activities are undertaken). 
NoiseNight 4 x Leq5 will be measured at NSR1, NSR2 and NSR3 during 23:00~07:00 of next day (if construction activities are undertaken).
NoisePH 6 x Leq5 will be measured at NSR1, NSR2 and NSR3 during 07:00~19:00 (if construction activities are undertaken).
Tentative Environmental Monitoring Schedule between 1-March 2006and 28-March 2006
Sunday   Monday    Tuesday   Wednesday   Thursday   Friday   Saturday  
              1-Mar   2-Mar   3-Mar   4-Mar
                24hrs-TSP 1hr-TSP      
            Noise      
            NoiseEvening  
                    NoiseNight    
  5-Mar   6-Mar   7-Mar   8-Mar   9-Mar   10-Mar   11-Mar
NoisePH           24hrs-TSP 1hr-TSP          
          Noise        
          NoiseEvening    
                NoiseNight        
  12-Mar   13-Mar   14-Mar   15-Mar   16-Mar   17-Mar   18-Mar
NoisePH       24hrs-TSP 1hr-TSP              
        Noise          
        NoiseEvening      
            NoiseNight            
  19-Mar   20-Mar   21-Mar   22-Mar   23-Mar   24-Mar   25-Mar
NoisePH   24hrs-TSP 1hr-TSP               24hrs-TSP
      Noise          
      NoiseEvening        
        NoiseNight                
  26-Mar   27-Mar   28-Mar                
NoisePH   1hr-TSP                      
    Noise              
    NoiseEvening          
    NoiseNight                    
1hr-TSP  3 x 1 hour TSP monitoring at ASR1, ASR2 and ASR3 during 09:00~18:00.
24hrs-TSP 24 hours TSP monitoring at ASR1, ASR2 and ASR3
Noise Leq30 measurement at NSR1, NSR2 and NSR3 during 07:00~19:00.
NoiseEvening 6 x Leq5 will be measured at NSR1, NSR2 and NSR3 during 19:00~23:00 (if construction activities are undertaken). 
NoiseNight 4 x Leq5 will be measured at NSR1, NSR2 and NSR3 during 23:00~07:00 of next day (if construction activities are undertaken).
NoisePH 6 x Leq5 will be measured at NSR1, NSR2 and NSR3 during 07:00~19:00 (if construction activities are undertaken).
Tentative Environmental Monitoring Schedule between 29-March 2006and 28-April 2006
Sunday   Monday    Tuesday   Wednesday   Thursday   Friday   Saturday  
              29-Mar   30-Mar   31-Mar   1-Apr
                    24hrs-TSP 1hr-TSP  
                   
               
                           
  2-Apr   3-Apr   4-Apr   5-Apr   6-Apr   7-Apr   8-Apr
NoisePH               24hrs-TSP 1hr-TSP      
              Noise      
              NoiseEvening  
                    NoiseNight    
  9-Apr   10-Apr   11-Apr   12-Apr   13-Apr   14-Apr   15-Apr
NoisePH           24hrs-TSP 1hr-TSP          
          Noise          
          NoiseEvening        
                NoiseNight        
  16-Apr   17-Apr   18-Apr   19-Apr   20-Apr   21-Apr   22-Apr
NoisePH       24hrs-TSP 1hr-TSP              
          Noise        
          NoiseEvening      
            NoiseNight            
  23-Apr   24-Apr   25-Apr   26-Apr   27-Apr   28-Apr   29-Apr
NoisePH   24hrs-TSP 1hr-TSP                  
      Noise            
      NoiseEvening        
        NoiseNight                
1hr-TSP  3 x 1 hour TSP monitoring at ASR1, ASR2 and ASR3 during 09:00~18:00.
24hrs-TSP 24 hours TSP monitoring at ASR1, ASR2 and ASR3
Noise Leq30 measurement at NSR1, NSR2 and NSR3 during 07:00~19:00.
NoiseEvening 6 x Leq5 will be measured at NSR1, NSR2 and NSR3 during 19:00~23:00 (if construction activities are undertaken). 
NoiseNight 4 x Leq5 will be measured at NSR1, NSR2 and NSR3 during 23:00~07:00 of next day (if construction activities are undertaken).
NoisePH 6 x Leq5 will be measured at NSR1, NSR2 and NSR3 during 07:00~19:00 (if construction activities are undertaken).