| Tentative Environmental Monitoring Schedule between 29-January
2006and 28-February 2006 |
|
|
|
|
|
| Sunday |
|
Monday |
|
Tuesday |
|
Wednesday |
|
Thursday |
|
Friday |
|
Saturday |
|
|
| |
29-Jan |
|
30-Jan |
|
31-Jan |
|
1-Feb |
|
2-Feb |
|
3-Feb |
|
4-Feb |
|
| |
|
|
|
|
|
24hrs-TSP |
1hr-TSP |
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
Noise |
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
NoiseEvening |
|
|
|
|
|
| |
|
|
|
|
|
|
|
NoiseNight |
|
|
|
|
|
| |
5-Feb |
|
6-Feb |
|
7-Feb |
|
8-Feb |
|
9-Feb |
|
10-Feb |
|
11-Feb |
|
| NoisePH |
|
|
|
24hrs-TSP |
1hr-TSP |
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
Noise |
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
NoiseEvening |
|
|
|
|
|
|
|
| |
|
|
|
|
|
NoiseNight |
|
|
|
|
|
|
|
| |
12-Feb |
|
13-Feb |
|
14-Feb |
|
15-Feb |
|
16-Feb |
|
17-Feb |
|
18-Feb |
|
| NoisePH |
|
24hrs-TSP |
1hr-TSP |
|
|
|
|
|
|
|
24hrs-TSP |
|
| |
|
|
|
Noise |
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
NoiseEvening |
|
|
|
|
|
|
|
|
|
| |
|
|
|
NoiseNight |
|
|
|
|
|
|
|
|
|
| |
19-Feb |
|
20-Feb |
|
21-Feb |
|
22-Feb |
|
23-Feb |
|
24-Feb |
|
25-Feb |
|
| NoisePH |
|
1hr-TSP |
|
|
|
|
|
|
|
24hrs-TSP |
1hr-TSP |
|
|
| |
|
Noise |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
NoiseEvening |
|
|
|
|
|
|
|
|
|
|
|
| |
|
NoiseNight |
|
|
|
|
|
|
|
|
|
|
|
| |
26-Feb |
|
27-Feb |
|
28-Feb |
|
|
|
|
|
|
|
|
|
| NoisePH |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 1hr-TSP |
3 x 1 hour TSP monitoring at ASR1, ASR2 and
ASR3 during 09:00~18:00. |
|
|
|
|
|
|
|
|
| 24hrs-TSP |
24 hours TSP monitoring at ASR1, ASR2 and ASR3 |
|
|
|
|
|
|
|
|
|
|
| Noise |
Leq30 measurement at NSR1, NSR2 and NSR3 during 07:00~19:00. |
|
|
|
|
|
|
|
|
| NoiseEvening |
6 x Leq5 will be measured at NSR1, NSR2 and NSR3 during 19:00~23:00
(if construction activities are undertaken). |
|
|
|
|
|
| NoiseNight |
4 x Leq5 will be measured at NSR1, NSR2 and NSR3 during 23:00~07:00
of next day (if construction activities are undertaken). |
|
|
|
|
| NoisePH |
6 x Leq5 will be measured at NSR1, NSR2 and NSR3 during 07:00~19:00
(if construction activities are undertaken). |
|
|
|
|
|
| Tentative
Environmental Monitoring Schedule between 1-March 2006and 28-March 2006 |
|
|
|
|
|
|
| Sunday |
|
Monday |
|
Tuesday |
|
Wednesday |
|
Thursday |
|
Friday |
|
Saturday |
|
|
| |
|
|
|
|
|
|
1-Mar |
|
2-Mar |
|
3-Mar |
|
4-Mar |
|
| |
|
|
|
|
|
|
|
24hrs-TSP |
1hr-TSP |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
Noise |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
NoiseEvening |
|
|
|
| |
|
|
|
|
|
|
|
|
|
NoiseNight |
|
|
|
| |
5-Mar |
|
6-Mar |
|
7-Mar |
|
8-Mar |
|
9-Mar |
|
10-Mar |
|
11-Mar |
|
| NoisePH |
|
|
|
|
|
24hrs-TSP |
1hr-TSP |
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
Noise |
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
NoiseEvening |
|
|
|
|
|
| |
|
|
|
|
|
|
|
NoiseNight |
|
|
|
|
|
| |
12-Mar |
|
13-Mar |
|
14-Mar |
|
15-Mar |
|
16-Mar |
|
17-Mar |
|
18-Mar |
|
| NoisePH |
|
|
|
24hrs-TSP |
1hr-TSP |
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
Noise |
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
NoiseEvening |
|
|
|
|
|
|
|
| |
|
|
|
|
|
NoiseNight |
|
|
|
|
|
|
|
| |
19-Mar |
|
20-Mar |
|
21-Mar |
|
22-Mar |
|
23-Mar |
|
24-Mar |
|
25-Mar |
|
| NoisePH |
|
24hrs-TSP |
1hr-TSP |
|
|
|
|
|
|
|
24hrs-TSP |
|
| |
|
|
|
Noise |
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
NoiseEvening |
|
|
|
|
|
|
|
|
|
| |
|
|
|
NoiseNight |
|
|
|
|
|
|
|
|
|
| |
26-Mar |
|
27-Mar |
|
28-Mar |
|
|
|
|
|
|
|
|
|
| NoisePH |
|
1hr-TSP |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
Noise |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
NoiseEvening |
|
|
|
|
|
|
|
|
|
|
|
| |
|
NoiseNight |
|
|
|
|
|
|
|
|
|
|
|
| 1hr-TSP |
3 x 1 hour TSP monitoring at ASR1, ASR2 and
ASR3 during 09:00~18:00. |
|
|
|
|
|
|
|
|
| 24hrs-TSP |
24 hours TSP monitoring at ASR1, ASR2 and ASR3 |
|
|
|
|
|
|
|
|
|
|
| Noise |
Leq30 measurement at NSR1, NSR2 and NSR3 during 07:00~19:00. |
|
|
|
|
|
|
|
|
| NoiseEvening |
6 x Leq5 will be measured at NSR1, NSR2 and NSR3 during 19:00~23:00
(if construction activities are undertaken). |
|
|
|
|
|
| NoiseNight |
4 x Leq5 will be measured at NSR1, NSR2 and NSR3 during 23:00~07:00
of next day (if construction activities are undertaken). |
|
|
|
|
| NoisePH |
6 x Leq5 will be measured at NSR1, NSR2 and NSR3 during 07:00~19:00
(if construction activities are undertaken). |
|
|
|
|
|
| Tentative
Environmental Monitoring Schedule between 29-March 2006and 28-April 2006 |
|
|
|
|
|
|
| Sunday |
|
Monday |
|
Tuesday |
|
Wednesday |
|
Thursday |
|
Friday |
|
Saturday |
|
|
| |
|
|
|
|
|
|
29-Mar |
|
30-Mar |
|
31-Mar |
|
1-Apr |
|
| |
|
|
|
|
|
|
|
|
|
24hrs-TSP |
1hr-TSP |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
2-Apr |
|
3-Apr |
|
4-Apr |
|
5-Apr |
|
6-Apr |
|
7-Apr |
|
8-Apr |
|
| NoisePH |
|
|
|
|
|
|
|
24hrs-TSP |
1hr-TSP |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
Noise |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
NoiseEvening |
|
|
|
| |
|
|
|
|
|
|
|
|
|
NoiseNight |
|
|
|
| |
9-Apr |
|
10-Apr |
|
11-Apr |
|
12-Apr |
|
13-Apr |
|
14-Apr |
|
15-Apr |
|
| NoisePH |
|
|
|
|
|
24hrs-TSP |
1hr-TSP |
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
Noise |
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
NoiseEvening |
|
|
|
|
|
| |
|
|
|
|
|
|
|
NoiseNight |
|
|
|
|
|
| |
16-Apr |
|
17-Apr |
|
18-Apr |
|
19-Apr |
|
20-Apr |
|
21-Apr |
|
22-Apr |
|
| NoisePH |
|
|
|
24hrs-TSP |
1hr-TSP |
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
Noise |
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
NoiseEvening |
|
|
|
|
|
|
|
| |
|
|
|
|
|
NoiseNight |
|
|
|
|
|
|
|
| |
23-Apr |
|
24-Apr |
|
25-Apr |
|
26-Apr |
|
27-Apr |
|
28-Apr |
|
29-Apr |
|
| NoisePH |
|
24hrs-TSP |
1hr-TSP |
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
Noise |
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
NoiseEvening |
|
|
|
|
|
|
|
|
|
| |
|
|
|
NoiseNight |
|
|
|
|
|
|
|
|
|
| 1hr-TSP |
3 x 1 hour TSP monitoring at ASR1, ASR2 and
ASR3 during 09:00~18:00. |
|
|
|
|
|
|
|
|
| 24hrs-TSP |
24 hours TSP monitoring at ASR1, ASR2 and ASR3 |
|
|
|
|
|
|
|
|
|
|
| Noise |
Leq30 measurement at NSR1, NSR2 and NSR3 during 07:00~19:00. |
|
|
|
|
|
|
|
|
| NoiseEvening |
6 x Leq5 will be measured at NSR1, NSR2 and NSR3 during 19:00~23:00
(if construction activities are undertaken). |
|
|
|
|
|
| NoiseNight |
4 x Leq5 will be measured at NSR1, NSR2 and NSR3 during 23:00~07:00
of next day (if construction activities are undertaken). |
|
|
|
|
| NoisePH |
6 x Leq5 will be measured at NSR1, NSR2 and NSR3 during 07:00~19:00
(if construction activities are undertaken). |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|