ES 1
An Environmental Permit (EP-085/2000/C) was
granted to Highways Department by the Environmental Protection Department for
the construction of Route 8 Project between Tsing Yi and Cheung Sha Wan. This EP covers four phases of the Route 8 Project
namely Phase
ES 2
This is the 42nd monthly
Environmental Monitoring and Audit (EM&A) report for “Phase
ES 3 During the monitoring period, some of the major construction activities undertaken during normal hours are highlighted as follows:
i. excavation;
ii. traffic and utilities diversions;
iii. abutment construction;
iv. pier construction;
v. bridge deck construction;
vi. viaduct finishing;
vii. segment delivery, erection and fixing, and;
viii. deck parapet skin erection and fixing
ES 4 During the monitoring period, the major construction activities undertaken during evening, night time and Public Holidays are highlighted as follows:
i. Pier/portal construction;
ii.
segment delivery, fixing and
erection;
iii. bridge deck construction, and;
iv. deck parapet skin erection and fixing
ES 5
Monitoring of Total Suspended Particulates (TSP)
and Noise were carried out in accordance with the EM&A Manual. Weekly site audits were conducted by the ET
on
Air Quality
ES 6
A total of 54 sets of
Noise
ES 7
In
order to assess the construction noise impact effectively for all noise
monitoring locations (NSR
Daytime Monitoring
ES 8
A total of
Evening-time Monitoring
ES 9
A total of
Night-time Monitoring
ES 10
A total of
Public-holiday Monitoring
ES 11
A total of 9 sets of 6 x Leq(5min) measurements
were taken in public holidays (i.e. 0700 to
Water Quality
ES 12
A total of 3 Effluent Discharge Licenses were
granted by EPD. In accordance with the
conditions of the licenses, water sampling at designated discharge points shall
be carried out on a monthly basis for area P
ES 13
One water sample was taken on
ES 14
One water sample was taken on
Waste Management
ES 15 With effect from 6th February 2005, all inert C&D material had been disposed of at Tuen Mun Area 38 instead of KTBP. The trip ticket system has been implemented effectively during the reporting period.
ES 16
A total of
ES 17
On
Site Audit
ES 18 Weekly
site audits were carried out by the ET and the major findings are presented
below:
|
Item |
Findings |
Corrective and Preventive measures proposed by CHEC |
Effectiveness of measures |
|
|
Rubbish / debris /
sediment were accumulated in the u-channels and catchpit at P No treatment facilities for
the u-channel adjacent to Pier SB38 & SB39 at P |
The u-channels and catchpit had been cleared immediately after the site inspection. In addition, all temporary drainage and runoff control systems had been maintained properly on a weekly basis. For Pier SB38 and SB39, the slope formation had been completed and hydroseeding was carried out by CHEC by end of January 2006. Sandbags have been deployed in the u-channel as an interim measure. |
Completed and (Please refer to Appendix Q
Photo |
|
2 |
Oil stain on the
ground at area P |
The oil stain and contaminated soil had been cleared as chemical waste
and was temporarily stored in the Chemical Waste Storage Area on site. |
Completed and (Please refer to Appendix Q, Photo 6). |
|
3 |
Insufficient wheel
facilities were provided at roundabout CP3/CP4 and mud track were observed on
the public road. |
Ramps and high pressure water jets have been provided at the site
exits. Waste water generated from wheel washing water would be diverted back
to the site area for soakaway. In addition,
all the existing gullies within the roundabout had been blocked. |
Completed and (Please refer to Appendix Q, Photo 7 to 9). |
|
4 |
For area P |
Proper enclosure
(sheltered on top and the 3 sides) has been provided for the debagging and
cement mixing process. |
(Please refer to Appendix Q, Photo |
ES 1
The monthly IEC audit was carried on
|
Item |
Findings |
Corrective and Preventive measures proposed by CHEC |
Effectiveness of measures |
|
|
Insufficient wheel washing
facilities were provided at roundabout CP3/CP4 and mud trails were observed
on the public road. |
Ramps and high pressure water jets have been provided at the site
exits. Waste water generated from wheel washing water would be diverted back
to the site area for soakaway. In
addition, all the existing gullies within the roundabout had been blocked. |
Completed and (Please refer to Appendix Q, Photo 7 to 9). |
|
2 |
Inadequate
enclosure was provided for the concrete debagging and mixing facility at P |
Proper
enclosure has been provided for the
debagging and cement mixing process. |
Completed and (Please refer to Appendix Q, Photo |
|
3 |
No treatment
facilities were provided for the u-channel adjacent to Pier SB 38 & 39
near P |
Slope formation had been completed and hydroseeding was
carried out by CHEC by end of January 2006. Sandbags have been deployed in
the u-channel. |
The situation will be monitored by ET continuously. (Please refer to Appendix Q
Photo 4 to 5) |
ES 2 No EPD site inspections were carried out during the reporting period.
ES 3
The following permits / licenses have been
granted by EPD for the construction of the Phase
·
Environmental
Permit (EP-085/2000/C)
·
Chemical
Waste Producer Registration (WPN
– 52
·
3
Effluent Discharge Licences (EP482/269/0038/I; EP482/269/0039/I &
EP482/269/0040/I)
·
Complaint Log
ES 4 No environmental related complaints were received during the reporting period.
ES 5
A total of
Notifications of Summons and Prosecution
ES 6 Since the commencement of construction, no notifications of summons nor prosecution were received on the environmental performance for this Contract.
Future Key Issues
ES 7 The tentative program of major site activities as well as the impact prediction and control measures for the coming three months, i.e. February 2006 to April 2006 are summarized below:
|
Construction Works |
Major Impact Prediction |
Control Measures |
|
Utilities diversion; abutment and pier/portal construction,
segment erection and bridge deck construction. |
Air impact (dust and machine emission) |
i. Frequent watering of haul road and unpaved/exposed areas; ii. Frequent watering or covering stockpiles with tarpaulin or similar means; iii. Regular maintenance of onsite machinery and vehicles; and iv. Reinstate the after worked area by hydro-seed or similar means. |
|
Water quality impact (muddy run-off) |
v. Collecting and recycling of wastewater produced on-site if possible; vi. Perimeter protection such as sandbag barriers and sealing the bottom of concrete barrier to avoid run-off entering the existing storm water drainage system; vii. Diverting the collected effluent to de-silting facilities for treatment before discharge to public drains; and viii.Covering of exposed slope with tarpaulin or similar means during rainstorm |
|
|
Noise Impact |
ix. Scheduling of noisy construction activities if necessary to avoid persistent noisy operation; x. Controlling the number of plants use on site; xi. Regular maintenance of machines; and xii. Use of acoustic barriers if necessary. |