7
AUDIT RESULTS
7.1.1
For
7.1.2
For 24-hour TSP monitoring, a total of
7.2.1
A total of
7.2.2
A total of 9 sets of 6 x Leq(5min) measurements were
taken in the evening-time (i.e.
7.2.3
A total of 9 sets of 4 x Leq(5min) measurements were
taken in the night-time (i.e. 2300 to 0700 next day) at all three monitoring
stations during the reporting period and no exceedances
were recorded.
7.2.4
A total of
7.3.1
A total of 3 Effluent Discharge Licenses were
granted by EPD. In accordance with the
conditions of the licenses, water sampling at designated discharge points shall
be carried out on a monthly basis for area P
7.3.2
Two water
samples were taken on
7.3.3
For area P
7.4.1
Waste generated from the Phase
7.4.2
With effect from
7.4.3
On
7.4.4
Based on the information provided by CHEC with
respect to relevant handling records and trip tickets of the Phase
Table
7.
|
Material
Type |
Quantity
Produced in the reporting period |
Handling
Method |
Handling
Quantities in the reporting month |
Temporary Storage Locations On-site (if
applicable) |
|
|
C&D
materials |
(Public Fill) |
47 |
Tuen Mun Fill Bank |
2,826m3 (2,820m3 to Tuen
Mun Area 38 & 6m3 to TKO Sorting
Facilities) |
N/A |
|
(C&D Waste) |
N/A |
To be recycled (paper) |
N/A |
P |
|
|
N/A |
To be recycled (aluminum
can) |
N/A |
P |
||
|
N/A |
To be recycled (plastic
bottle) |
N/A |
P |
||
|
N/A |
To be reused |
N/A |
P |
||
|
N/A |
To be returned to supplier |
N/A |
P |
||
|
|
Collected by licensed
collector for disposal to SENT and WENT landfills |
|
N/A |
||
|
Chemical waste |
(spent oil) & 60kg (contaminated soil) |
Collected by licensed
chemical waste collector |
(spent oil) & 60kg (contaminated soil) |
N/A |
|
7.5.1
Scheduled site audits were carried out by the ET
and IEC on a regular basis in accordance with the EM&A Manual. Sections below provide a detail summary of
the findings identified during these audits and their corresponding implemented
corrective and preventive measures.
Photographs of implemented measures are presented in Appendix Q.
7.5.2
Weekly site inspections were conducted by the ET
during the reporting period and the major findings are summarized as follows:
i.
Stagnant
water / sediment / debris / sand were accumulated in the drainage systems at
areas P
Corrective
and Preventive Actions – The u-channels and catchpits had been cleared
immediately after the site inspections.
In addition, all temporary drainage and runoff control systems had been
maintained properly on a weekly basis. Completed and
ii.
Oil
stain on the ground and oily water in the drip tray were observed at P
Corrective and Preventive Actions - The oily water,
oil stain and contaminated soil had been cleared as chemical waste and
temporarily stored in the Chemical Waste Storage Area on site at P
iii.
Rubbish
accumulated at P
Corrective and
Preventive Actions – Rubbish in
the concerned areas had been cleaned immediately after site inspections. Completed and
iv.
As the
wet season is approaching, CHEC
was reminded that all surface
runoff should be properly treated before discharge to existing storm drains and
the maintenance procedure should be carried out in accordance with the
Environmental Permit.
Corrective and
Preventive Actions – All temporary
systems and wastewater treatment facilities have been maintained properly on a
weekly basis. In addition, 4 submersible pumps had been installed for the drainage
system at P
Independent Environmental Checker (IEC) Site Audits
7.5.3
The monthly IEC audit was carried out on
Environmental
Protection Department (EPD)
Site Inspections
7.5.4
No EPD site inspections were carried out during the
reporting period.