ES 1
An Environmental Permit (EP-085/2000/C) was
granted to Highways Department by the Environmental Protection Department for
the construction of Route 8 Project between Tsing Yi and Cheung Sha Wan. This EP covers four phases of the Route 8
Project namely Phase
ES 2
This is the 46th monthly Environmental
Monitoring and Audit (EM&A) report for “Phase
ES 3 During the monitoring period, some of the major construction activities undertaken during normal hours are highlighted as follows:
i. excavation;
ii. traffic and utilities diversions;
iii. abutment backfilling;
iv. pier/portal construction;
v. bridge deck construction;
vi. viaduct finishing and surfacing;
vii. drainage system installation;
viii. segment delivery, erection and fixing; and
ix. deck parapet skin erection and fixing.
ES
4
During the monitoring period, the major
construction activities undertaken during evening, night time and Public
Holidays are highlighted as follows:
i. pier/portal construction;
ii.
segment delivery, fixing and
erection;
iii. bridge deck construction; and
iv. deck parapet skin erection and fixing.
ES
5
Monitoring of Total Suspended Particulates (TSP)
and Noise were carried out in accordance with the EM&A Manual. Weekly site inspections were conducted by the
ET on 4th,
Air Quality
ES 6
A total of 54 sets of
Noise
ES 7
In
order to assess the construction noise impact effectively for all noise
monitoring locations (NSR
Daytime Monitoring
ES 8
A total of
Evening-time Monitoring
ES 9
A total of 9 sets of 6 x Leq(5min) measurements
were taken in the evening-time (i.e.
Night-time Monitoring
ES 10 A total of 9 sets of 4 x Leq(5min) measurements were taken at night-time (i.e. 2300 to 0700 next day) at all three monitoring stations during the reporting period and no exceedances were recorded.
Public-holiday Monitoring
ES 11
A total of 9 sets of 6 x Leq(5min) measurements
were taken in public holidays (i.e. 0700 to
Water Quality
ES 12
A total of 3 Effluent Discharge Licenses were
granted by EPD. In accordance with the
conditions of the licenses, water sampling at designated discharge points shall
be carried out on a monthly basis for area P
ES 13
5 water samples (3 at P
Waste Management
ES 14
A revised Waste Management Plan (Rev.
ES 15
With effect from
ES 16
A total of 522 no. of trucks (approximately 3,
ES 17
On
Site Audits / Inspections
ES
18
Weekly site inspections were carried out by the
ET and the major findings are presented below:
|
Item |
Findings |
Corrective and Preventive measures proposed by CHEC |
Effectiveness of measures |
|
|
CHEC
was reminded to cover all open stockpiles entirely by impervious sheeting
after operation and / or end of each working day. |
For
open stockpiling areas at P The
remaining open stockpiles / soil heaps on site have been covered by impervious sheeting
properly after operation and / or end of each working day. |
Completed and |
|
2 |
CHEC
was reminded to maintain all silt removal facilities, channels and manholes
with the deposited silt and grit being removed at least once a week, and at
the onset of and after each rainstorm. |
All
temporary drainage and runoff control systems would be maintained properly on
a weekly basis, and at the onset of and after each rainstorm. |
Completed and (Please refer to Appendix Q, Photo 5 to 8). |
ES
1
The monthly IEC audit was carried out on
ES 2
EPD site inspection was carried out on
ES
3
The following permits / licenses have been
granted by EPD for the construction of the Phase
·
Environmental
Permit (EP-085/2000/C)
·
Chemical
Waste Producer Registration (WPN
– 52
·
3
Effluent Discharge Licences (EP482/269/0038/I; EP482/269/0039/I &
EP482/269/0040/I)
·
6
Construction Noise Permits.
Environmental Complaints
ES 4 No environmental complaints were received during the reporting period.
ES 5
A total of
Notifications of Summons and Prosecution
ES 6 Since the commencement of construction, no notifications of summons nor prosecution were received on the environmental performance for this Contract.
Future Key Issues
ES 7 The tentative program of major site activities as well as the impact prediction and control measures for the coming three months, i.e. June 2006 to August 2006 are summarized below:
|
Construction Works |
Major Impact Prediction |
Control Measures |
|
Utilities
diversion; abutment and pier/portal construction, segment erection and
bridge deck construction. |
Air impact (dust and machine emission) |
i. Frequent watering of haul road and unpaved/exposed areas; ii. Frequent watering or covering stockpiles with tarpaulin or similar means; iii. Regular maintenance of onsite machineries and vehicles; and iv. Reinstate the worked area by hydro-seed or similar means. |
|
Water quality impact (muddy run-off) |
v. Collecting and recycling of wastewater produced on-site if possible; vi. Perimeter protection such as sandbag barriers and sealing the bottom of concrete barrier to avoid run-off entering the existing storm water drainage system; vii. Diverting the collected effluent to de-silting facilities for treatment before discharge to public drains; and viii.Covering of exposed slope with tarpaulin or similar means during rainstorm |
|
|
Noise Impact |
ix. Scheduling of noisy construction activities if necessary to avoid persistent noisy operation; x. Controlling the number of plants use on site; xi. Regular maintenance of machines; and xii. Use of acoustic barriers if necessary. |