7.1.1
For
7.1.2
For 24-hour TSP
monitoring, a total of
7.2.1
A total of
7.2.2
A total of 9 sets of 6 x Leq(5min) measurements were taken in the
evening-time (i.e.
7.2.3
A total of 9 sets of 4 x Leq(5min) measurements were taken in the
night-time (i.e. 2300 to 0700 next day) at all three monitoring stations during
the reporting period and no exceedances were recorded.
7.2.4
A total of 9 sets of 6 x Leq(5min) measurements were taken in public holidays (i.e.
0700 to
7.3.1
A total of 3
Effluent Discharge Licenses were granted by EPD. In accordance with the conditions of the
licenses, water sampling at designated discharge points shall be carried out on
a monthly basis for area P
7.3.2
5 water samples (3 at P
7.4.1
Waste generated from
the Phase
7.4.2
A revised WMP (Rev.
7.4.3
With effect from
7.4.4
On
7.4.5
Based on the
information provided by CHEC with respect to relevant handling records and trip
tickets of the Phase
Table 7.
|
Material
Type |
Quantity
Produced in the reporting period |
Handling
Method |
Handling
Quantities in the reporting month |
Temporary Storage Locations On-site (if
applicable) |
|
|
C&D
materials |
(Public Fill) |
522 no. of Trucks |
Tuen Mun Fill Bank (Tuen Mun Area 38) |
3, |
N/A |
|
(C&D Waste) |
N/A |
To be recycled (paper) |
N/A |
P |
|
|
N/A |
To be recycled (aluminum
can) |
N/A |
P |
||
|
N/A |
To be recycled (plastic
bottle) |
N/A |
P |
||
|
N/A |
To be reused |
N/A |
P |
||
|
N/A |
To be returned to supplier |
N/A |
P |
||
|
|
Collected by licensed
collector for disposal to SENT and WENT landfills |
|
N/A |
||
|
Chemical waste |
N/A |
Collected by licensed
chemical waste collector |
N/A |
N/A |
|
7.5.1
Scheduled site
audits were carried out by the ET and IEC on a regular basis in accordance with
the EM&A Manual. Sections below
provide a detail summary of the findings identified during these audits and
their corresponding implemented corrective and preventive measures. Photographs of implemented measures are
presented in Appendix Q.
Environmental Team Site Inspections
7.5.2
Weekly site
inspections were conducted by the ET during the reporting period and the major
findings are summarized as follows:
i.
CHEC was reminded to
cover all open stockpiles entirely by impervious sheeting after operation and /
or end of each working day.
Corrective
and Preventive Actions – For open stockpiling areas at P
ii.
CHEC was reminded to
maintain all silt removal facilities, channels and manholes with the deposited
silt and grit being removed at least once a week, and at the onset of and after
each rainstorm.
Corrective and Preventive Actions - All
temporary drainage and runoff control systems would be maintained properly on a
weekly basis, and at the onset of and
after each rainstorm. Completed and
Independent Environmental Checker (IEC) Site Audit
7.5.3
The monthly IEC
audit was carried out on
Environmental Protection
Department (EPD)
Site Inspections
7.5.4
EPD site inspection
was carried out on