ES 1
An Environmental Permit (EP-085/2000/C) was
granted to Highways Department by the Environmental Protection Department for
the construction of Route 8 Project between Tsing Yi and Cheung Sha Wan. This EP covers four phases of the Route 8
Project namely Phase
ES 2
This is the 47th monthly Environmental
Monitoring and Audit (EM&A) report for “Phase
ES 3 During the monitoring period, some of the major construction activities undertaken during normal hours are highlighted as follows:
i. excavation;
ii. traffic and utilities diversions;
iii. abutment backfilling;
iv. pier/portal construction;
v. bridge deck construction;
vi. viaduct finishing and surfacing,
vii. drainage system installation;
viii. segment delivery, erection and fixing; and
ix. deck parapet skin erection and fixing.
ES 4 During the monitoring period, the major construction activities undertaken during evening, night time and Public Holidays are highlighted as follows:
i. pier/portal construction;
ii.
segment delivery, fixing and
erection; and
iii. deck parapet skin erection and fixing.
ES 5
Monitoring of Total Suspended Particulates (TSP)
and Noise were carried out in accordance with the EM&A Manual. Weekly site inspections were conducted by the
ET on 2nd, 9th,
Air Quality
ES 6
A total of 45 sets of
Noise
ES 7
In
order to assess the construction noise impact effectively for all noise
monitoring locations (NSR
Daytime Monitoring
ES 8
A total of
Evening-time Monitoring
ES 9
A total of 9 sets of 6 x Leq(5min) measurements
were taken in the evening-time (i.e.
Night-time Monitoring
ES 10 A total of 9 sets of 4 x Leq(5min) measurements were taken at night-time (i.e. 2300 to 0700 next day) at all three monitoring stations during the reporting period and no exceedances were recorded.
Public-holiday Monitoring
ES 11
A total of 7 sets of 6 x Leq(5min) measurements
were taken in public holidays (i.e. 0700 to
Water Quality
ES 12
A total of 3 Effluent Discharge Licenses were
granted by EPD. In accordance with the
conditions of the licenses, water sampling at designated discharge points shall
be carried out on a monthly basis for area P
ES 13
3 water samples at P
Waste Management
ES 14
A revised Waste Management Plan (Rev.
ES 15
With effect from
ES 16
A total of 397 no. of trucks (approximately
2,382m3) of inert C&D materials were delivered to Tuen Mun Fill Bank
during the reporting period. Approximate
ES 17
On
Site Audits / Inspections
ES 18 Weekly
site inspections were carried out by the ET and the major findings are
presented below:
|
Item |
Findings |
Corrective and Preventive measures proposed by CHEC |
Effectiveness of measures |
|
|
Sandbags along the
u-channels at P Sediment was
accumulated in the u-channels at Grid 7 of P Silty /standing
water was accumulated in the u-channel (next to gantry) and sedimentation
tank No. 7 at P |
Damaged sandbags
along the u-channels had been replaced. All u-channels had
been cleared immediately after the site inspections. In addition, all
temporary drainage and runoff control systems have been maintained properly
on a weekly basis. |
Completed and |
|
2 |
Open stockpiles
without entirely covered by impervious sheeting at P |
Open stockpiles at
P For area P |
Completed and (Please
refer to Appendix Q, Photo |
ES 1
The monthly IEC audit was carried out on
|
Observation(s) |
|||
|
Item |
Findings |
Corrective and Preventive measures proposed by CHEC |
Effectiveness of measures |
|
|
Standing water and
deposited grit/ silt were found accumulating at the u-channels next to the gantry
and the sedimentation tank no. 7 at P CHEC was urged to
clean up the u-channel and the sedimentation tank immediately, and also
properly maintain all drainage system at least once a week. |
All u-channels and
sedimentation tanks had been cleared immediately after the site audit. In addition, all
temporary drainage and runoff control systems have been maintained properly
on a weekly basis. |
Completed and |
|
Reminder(s) |
|||
|
|
Accumulation of stagnant water was observed at various
locations in P |
Stagnant water had been cleared as far as possible. The routine anti-mosquito breeding measures have been enhanced to reduce the risk of mosquito breeding. Larvicidal oil had been applied to places where they are not easily assessable at least twice a week. |
The measures provided were effective and situation would be monitored continuously. (Please refer to Appendix Q,
Photo |
ES 2 No joint inspections were carried out with EPD during the reporting month.
ES 3
The following permits / licenses have been
granted by EPD for the construction of the Phase
·
Environmental
Permit (EP-085/2000/C)
·
Chemical
Waste Producer Registration (WPN
– 52
·
3
Effluent Discharge Licences (EP482/269/0038/I; EP482/269/0039/I &
EP482/269/0040/I)
·
5
Construction Noise Permits.
Environmental Complaints
ES 4 No environmental complaints were received during the reporting period.
ES 5
A total of
Notifications of Summons and Prosecution
ES 6 Since the commencement of construction, no notifications of summons nor prosecution were received on the environmental performance for this Contract.
Future Key Issues
ES 7 The tentative program of major site activities as well as the impact prediction and control measures for the coming three months, i.e. July 2006 to September 2006 are summarized below:
|
Construction Works |
Major Impact Prediction |
Control Measures |
|
Utilities diversion; abutment and pier/portal construction,
segment erection and bridge deck construction. |
Air impact (dust and machine emission) |
i. Frequent watering of haul road and unpaved/exposed areas; ii. Frequent watering or covering stockpiles with tarpaulin or similar means; iii. Regular maintenance of onsite machineries and vehicles; and iv. Reinstate the worked area by hydro-seed or similar means. |
|
Water quality impact (muddy run-off) |
i. Collecting and recycling of wastewater produced on-site if possible; ii. Perimeter protection such as sandbag barriers and sealing the bottom of concrete barrier to avoid run-off entering the existing storm water drainage system; iii. Diverting the collected effluent to de-silting facilities for treatment before discharge to public drains; and iv. Covering of exposed slope with tarpaulin or similar means during rainstorm |
|
|
Noise Impact |
i. Scheduling of noisy construction activities if necessary to avoid persistent noisy operation; ii. Controlling the number of plants use on site; iii. Regular maintenance of machines; and iv. Use of acoustic barriers if necessary. |