7 AUDIT RESULTS
7.1.1
For
7.1.2
For 24-hour TSP monitoring, a total of
7.2.1
A total of
7.2.2
A total of
7.2.3
A total of
7.2.4
A total of 9 sets of 6 x Leq(5min)
measurements were taken in public holidays (i.e. 0700 to
7.3.1
A total of 3 Effluent Discharge Licenses were
granted by EPD. In accordance with the
conditions of the licenses, water sampling at designated discharge points shall
be carried out on a monthly basis for area P
7.3.2
Nine water
samples were taken for the whole construction site on
7.4.1
Waste generated from the Phase
7.4.2
A revised WMP (Rev.
7.4.3
With effect from
7.4.4
On
7.4.5
Based on the information provided by CHEC with
respect to relevant handling records and trip tickets of the Phase
Table
7.
|
Material
Type |
Quantity
Produced in the reporting period |
Handling
Method |
Handling
Quantities in the reporting month |
Temporary Storage Locations On-site (if
applicable) |
|
|
C&D
materials |
(Public
Fill) |
|
Tuen Mun Fill Bank (Tuen
Mun Area 38) |
|
N/A |
|
(C&D Waste) |
N/A |
To be recycled (paper) |
N/A |
P |
|
|
N/A |
To be recycled (aluminum
can) |
N/A |
P |
||
|
N/A |
To be recycled (plastic
bottle) |
N/A |
P |
||
|
N/A |
To be reused |
N/A |
P |
||
|
N/A |
To be returned to supplier |
N/A |
P |
||
|
|
Collected by licensed
collector for disposal to SENT and WENT landfills |
|
N/A |
||
|
Chemical waste |
N/A |
Collected by licensed chemical
waste collector |
944 litres of spent lube
oil |
P |
|
7.5.1 Scheduled site audits were carried out by the ET and IEC on a regular basis in accordance with the EM&A Manual. Sections below provide a detail summary of the findings identified during these audits and their corresponding implemented corrective and preventive measures. Photographs of implemented measures are presented in Appendix Q.
Environmental Team Site Inspections
7.5.2 Weekly site inspections were conducted by the ET during the reporting period and the major findings are summarized as follows:
i.
The chemical enhance treatment plant (CETP) at P
Corrective and
Preventive Actions The mentioned CETPs and
u-channels had been cleared immediately after the site inspections. In addition, all temporary drainage and
runoff control systems have been maintained properly on a weekly basis. Completed and
ii.
Mosquito larvae were found in stagnant water
accumulated on uneven ground of segment storage area at P
Corrective and Preventive Actions -
Stagnant water was cleared by CHEC immediately after the site audit. For P
In addition, larvicidal
oil / temephos had been applied to places where they
were not easily assessable at least twice a week to reduce the risk of mosquito
breeding on site. (Please refer Appendix Q
Photo 07). The situation
will be monitored by RSS and ET continuously.
iii.
Water pondings were
found at areas P
Corrective and Preventive Actions - Leveling of uneven ground and removal of
water pondings / stagnant water has been carried out
by CHEC wherever possible. All stagnant
water accumulated within steelworks had been removed after the site
inspections. Regular inspection has been
carried out by CHEC to ensure proper anti-mosquito measures have been adopted
on site. (Please refer Appendix Q Photo 08 to
iv.
Silty water was
observed discharging into storm drains via sedimentation tank no.7 at P
Corrective and Preventive Actions - For P
Independent Environmental Checker (IEC) Site Audit
7.5.3
The monthly IEC audit was carried out on
Observation(s)
i.
A significant amount of silt and grit was
accumulated in the chemical enhance treatment plant (CETP) at P
Corrective and
Preventive Actions All silt and
grit had been removed from the CETP after the site audit. Completed and
ii.
Silt,
grout and cables were found accumulating at the u-channel and ditch next to the
CETP at P
Corrective and
Preventive Actions The u-channel
and ditch had been cleared after the site audit. In addition, all temporary drainage systems
have been maintained properly at least once a weekly. Completed and
iii.
Standing
water and deposited silt was accumulated in the u-channels at P
Corrective and
Preventive Actions The mentioned u-channels had been cleaned immediately
after the site audit. Completed and
iv.
Mosquito larvae were found in stagnant water
accumulated on uneven ground next to the gantry at P
Corrective and
Preventive Actions Stagnant water was cleared by CHEC immediately after
the site audit. Sump pits and water
pumps have been deployed to divert stagnant water to treatment facilities prior
to discharge. Completed and
Environmental Protection Department (EPD) Site Inspections
7.5.4
A joint site inspection was carried out with EPD
on
i.
For area P
Corrective
and Preventive Actions All idle open stockpiles (not in operation) have
been covered by impervious sheeting and the remaining stockpile should be
covered by impervious sheeting after operation or sprayed with sufficient water
to maintain the entire surface moist.
Completed and
ii.
Part of the sandbag barrier along the u-channel
adjacent to CT8 at area P
Corrective
and Preventive Actions All damaged sandbags had been replaced immediately
after the joint site inspection. In
addition, the drainage systems including sandbag barriers have been regularly
maintained by CHEC on a weekly basis. Completed and