ES
1
An Environmental Permit (EP-085/2000/C) was
granted to Highways Department by the Environmental Protection Department for
the construction of Route 8 Project between Tsing Yi and Cheung Sha Wan. This EP covers four phases of the Route 8 Project
namely Phase
ES
2
This is the 49th monthly Environmental Monitoring and Audit (EM&A)
report for “Phase
ES
3
During the monitoring period, some of the major
construction activities undertaken during normal hours are highlighted as
follows:
i.
booster pump house
construction;
ii.
excavation;
iii.
traffic and utilities
diversions;
iv.
pier/portal construction;
v.
bridge deck construction;
vi.
viaduct finishing and surfacing,
vii.
drainage system installation;
viii.
segment delivery, erection and
fixing; and
ix.
deck parapet erection and fixing.
ES
4
During the monitoring period, the major
construction activities undertaken during evening, night time and Public
Holidays are highlighted as follows:
i.
Pier/portal construction;
ii.
segment delivery, fixing and
erection; and
iii.
deck parapet erection and fixing.
ES
5
Monitoring of Total Suspended Particulates (TSP)
and Noise were carried out in accordance with the EM&A Manual. Weekly site inspections were conducted by the
ET on 4th, 10th, 18th and 25th August
2006 and the joint IEC monthly audit was conducted on
Air Quality
ES
6
A total of 45 sets of
Noise
ES
7
In
order to assess the construction noise impact effectively for all noise
monitoring locations (NSR
Daytime Monitoring
ES
8
A total of 12 sets of Leq(30min)
measurement were taken in the daytime (i.e. 0700 to
Evening-time Monitoring
ES
9
A total of 12 sets of 6 x Leq(5min) measurements were taken in
the evening-time (i.e.
Night-time Monitoring
ES
10
A total of 1 set of 4 x Leq(5min)
measurements were taken at night-time (i.e. 2300 to 0700 next day) at all three
monitoring stations during the reporting period and no exceedances were
recorded.
Public-holiday Monitoring
ES
11
A total of 15 sets of 6 x Leq(5min)
measurements were taken in public holidays (i.e. 0700 to
Water Quality
ES
12
A total of 3 Effluent Discharge Licenses were
granted by EPD. In accordance with the
conditions of the licenses, water sampling at designated discharge points shall
be carried out on a monthly basis for area P
ES
13
Three water
samples were taken for P1-SA1
(Part 1, Grid 1 to 9) by CHEC on
Waste Management
ES
14
A revised Waste Management Plan (Rev. 17) was
submitted to EPD for information on 11th May 2006 with the latest
information including the most up to date estimation of inert C&D materials
and non-inert C&D materials
ES
15
With effect from
ES
16
A total of 282 no. of trucks (approximately 1,692m3) of inert C&D
materials were delivered to Tuen Mun Fill Bank during the reporting
period. Approximate 224 tonnes of
C&D waste was produced on-site and were delivered to SENT. In addition, no chemical waste was disposed
of site during the reporting period.
ES
17
On
Site Audits / Inspections
ES 18
Weekly site inspections were carried out by the
ET and the major findings are presented below:
|
Item |
Findings |
Corrective and Preventive measures
proposed by CHEC |
Effectiveness of measures |
|
1 |
Silt and standing water was
accumulated in the u-channels at areas P1-SA1, P |
The mentioned u-channels and
sedimentation tanks had been cleared immediately after the site inspections. In addition, all temporary drainage and
runoff control systems have been maintained properly on a weekly basis. |
Completed and (Please refer to Appendix Q, Photo 0 |
|
2 |
Mosquito larvae were found in
stagnant water within the steelwork at area P |
Stagnant water was cleared by CHEC
immediately after the site audit. In addition, larvicidal oil /
temephos had been applied to places where they were not easily accessible at
least twice a week to reduce the risk of mosquito breeding on site. |
Completed and (Please refer Appendix
Q Photo 05 & 06) The situation will be monitored by RSS and ET continuously. |
|
3 |
Stagnant water was found at P1-SA1
(Part 1, under segments and along gantry’s rail) and P |
All stagnant water had been removed
wherever possible after the site inspections.
Several holes were drilled at
appropriate locations along the concrete wall of the gantry in order to
improve the drainage system within this particular area. Regular inspections have been carried out
by CHEC to ensure proper anti-mosquito measures have been adopted on site. |
Completed and (Please refer Appendix
Q Photo 07 to The situation will be monitored by
RSS and ET continuously. |
|
4 |
Oil stains on the ground were
observed at areas P |
All contaminated material had been
cleared as chemical waste. |
Completed and (Please refer Appendix
Q Photo |
|
5 |
CHEC was reminded to cover all open stockpiles by impervious sheeting
at P1-SA1 (Part 2, Grid 25) to minimize the dust impact generated from
construction site. |
All open stockpiles (not in
operation) have been covered with impervious sheeting. |
Completed and (Please refer Appendix
Q Photo |
ES
19
The monthly IEC audit was carried out on
|
Item |
Findings |
Corrective and Preventive measures
proposed by CHEC |
Effectiveness of measures |
|
|
Silt and stagnant water were
accumulated at the u-channels at areas P |
The mentioned u-channels had been cleared immediately after the site audit and all temporary drainage and runoff control systems have been maintained properly on a weekly basis. In addition, all damaged geo-textile
for the protection of existing gullies had been replaced. |
Completed and (Please refer to Appendix Q, Photo 0 |
|
2 |
Oil stains were observed on the ground at areas P |
All contaminated material had been
cleared as chemical waste. |
Completed and (Please refer Appendix
Q Photo |
|
3 |
Standing water was accumulated on uneven ground near the site
exit/entrance and under Kinko's container (site office) at P1-SA1 (Part 2). |
All stagnant water had been removed
by CHEC wherever possible. Regular inspections have been carried out by CHEC
to ensure proper anti-mosquito measures have been carried out. |
Completed and (Please refer Appendix
Q Photo 09 & |
|
4 |
CHEC was reminded to cover all open stockpiles by impervious sheeting
at P1-SA1 (Part 2, Grid 25) to minimize the dust impact generated from
construction site. |
All open stockpiles (not in
operation) have been covered with impervious sheeting. |
Completed and (Please refer Appendix
Q Photo |
|
5 |
CHEC was urged to provide proper treatment facilities for the
wastewater generated from the wheel washing at P1-SA1 (Part 2, at Grid 26). |
The site exit had been Wheel washing facilities together
with proper treatment facilities should be provided for all site exits. |
Completed and (Please refer Appendix
Q Photo |
ES
20
No joint site inspections were carried out with
EPD during the reporting period.
ES
21
The following permits / licenses have been
granted by EPD for the construction of the Phase
i.
Environmental Permit
(EP-085/2000/C)
ii.
Chemical Waste Producer
Registration (WPN – 52
iii.
3 Effluent Discharge Licences
(EP482/269/0038/I; EP482/269/0039/I & EP482/269/0040/I)
iv.
5 Construction Noise Permits.
Environmental Complaints
ES
22
No environmental complaints were received during
the reporting period.
ES
23
A total of
Notifications of Summons and Prosecution
ES
24
Since the commencement of construction, no
notifications of summons nor prosecution were received on the environmental
performance for this Contract.
Future Key Issues
ES
25
The tentative program of major site activities
as well as the impact prediction and control measures for the coming three
months, i.e. September 2006 to November
2006 are summarized below:
|
Construction Works |
Major Impact Prediction |
Control Measures |
|
Utilities diversions; booster pump
house, pier/portal construction, segment erection and bridge deck
construction. |
Air impact (dust and machine emission) |
i. Frequent
watering of haul road and unpaved/exposed areas; ii. Frequent
watering or covering stockpiles with tarpaulin or similar means; iii. Regular
maintenance of onsite machineries and vehicles; and iv. Reinstate
the worked area by hydro-seed or similar means. |
|
Water quality impact (muddy run-off) |
i. Collecting
and recycling of wastewater produced on-site if possible; ii. Perimeter
protection such as sandbag barriers and sealing the bottom of concrete
barrier to avoid run-off entering the existing storm water drainage system; iii. Diverting
the collected effluent to de-silting facilities for treatment before
discharge to public drains; and iv. Covering
of exposed slope with tarpaulin or similar means during rainstorm |
|
|
Noise Impact |
i. Scheduling
of noisy construction activities if necessary to avoid persistent noisy
operation; ii. Controlling
the number of plants use on site; iii. Regular
maintenance of machines; and iv. Use
of acoustic barriers if necessary. |