7
AUDIT RESULTS
7.1.1
For
7.1.2
For 24-hour TSP monitoring, a total of
7.2.1
A total of
7.2.2
A total of
7.2.3
A total of 5 set of 4 x Leq(5min)
measurements were taken in the night-time (i.e. 2300 to 0700 next day) at the
7.2.4
A total of
7.3.1
A total of 3 Effluent Discharge Licenses were
granted by EPD. In accordance with the
conditions of the licenses, water sampling at designated discharge points shall
be carried out on a monthly basis for area P
7.3.2
Three water samples
were taken for P
7.3.3
Three water samples were taken for P
7.4
Waste Management
7.4.1
Waste generated from the Phase
7.4.2
A revised WMP (Rev.
7.4.3
With effect from
7.4.4
On
7.4.5
Based on the information provided by CHEC with
respect to relevant handling records and trip tickets of the Phase
Table
7.
|
Material
Type |
Quantity
Produced in the reporting period |
Handling
Method |
Handling
Quantities in the reporting month |
Temporary Storage Locations On-site (if
applicable) |
|
|
C&D
materials |
(Public
Fill) |
537 no. of Trucks |
Tuen Mun Fill Bank (536
nos. of trucks to Tuen Mun
Area 38 and |
Approx. 2,4 |
N/A |
|
(C&D Waste) |
N/A |
To be recycled (paper) |
N/A |
P |
|
|
N/A |
To be recycled (aluminum
can) |
N/A |
P |
||
|
N/A |
To be recycled (plastic
bottle) |
N/A |
P |
||
|
N/A |
To be reused |
N/A |
P |
||
|
N/A |
To be returned to supplier |
N/A |
P |
||
|
98.9 |
Collected by licensed
collector for disposal to SENT and WENT landfills |
98.9 |
N/A |
||
|
Chemical waste |
N/A |
Collected by licensed
chemical waste collector |
N/A |
P |
|
7.5.1
Scheduled site audits were carried out by the ET
and IEC on a regular basis in accordance with the EM&A Manual. Sections below provide a detail summary of
the findings identified during these audits and their corresponding implemented
corrective and preventive measures.
Photographs of implemented measures are presented in Appendix Q.
7.5.2
Weekly site inspections were conducted by the ET
during the reporting period and the major findings are summarized as follows:
i.
Open stockpiles of dusty materials were observed
at areas P
Corrective and
Preventive Actions All idled open stockpiles (not in operation) have been
covered by impervious sheeting and the remaining stockpiles should be covered by impervious sheeting
after operation or at the end of each working day. Completed and
ii.
Standing water and silt were accumulated in the
sedimentation tank, catchpit and u-channels at area P
Corrective and
Preventive Actions - The temporary drainage system and treatment facilities
had been cleared immediately after the site inspection. Completed and
iii.
Stagnant water was accumulated on uneven ground
at P
Corrective and
Preventive Actions - All stagnant water had been removed wherever
possible. Larvicidal
oil / temephos have been applied to places where they
were not easily accessable to reduce the risk of
mosquito breeding. Regular inspections
have been carried out by CHEC to ensure proper anti-mosquito measures have been
adopted on site. Completed and
Independent Environmental Checker (IEC) Site Audit
7.5.3
The monthly IEC audit was carried out on
i.
Open stockpiles of dusty materials were observed
at areas P
Corrective and
Preventive Actions All idled open stockpiles (not in operation) have been
covered by impervious sheeting and the remaining stockpiles should be covered by impervious sheeting
after operation or end of each working day.
Completed and
ii.
Standing water and silt were accumulated in the
sedimentation tank, catchpit and u-channels at area P
Corrective and
Preventive Actions - The temporary drainage system and treatment facilities
had been cleared immediately after the site inspection. Completed and
Environmental
Protection Department (EPD) Site Inspections
7.5.4
A joint site inspection was carried out with EPD
on
i.
For area P
Corrective and Preventive Actions All idled open stockpiles (not in operation)
have been covered by impervious sheeting and the remaining stockpiles should be covered by impervious sheeting after operation or at
the end of each working day. (Please
refer to Appendix Q, Photo 02).
ii.
All silt removal facilities, u-channels,
catchpits and manholes shall be suitably maintained with the deposited silt and
grit being removed at least once a week.
Corrective and Preventive Actions A
iii.
All
C&D materials to be delivered off site to designated public filling area /
landfills should strictly follow the contract specifications and appropriate
Environmental Ordinances.
Corrective and Preventive Actions The trip ticket and chits systems have been
implemented properly for the removal of C&D materials from site to designated disposal locations. The
systems / situation will be monitored by CHEC, RSS and ET continuously.