Appendix I: Implementation Status of
Environmental Protection Requirement
|
Environmental Protection
Measures |
Timing |
Implementation Stages* |
||||
|
Activities |
|
|
|
|
|
|
|
Landscape
and visual |
Erection,
painting and maintenance of site hoardings around works and storage areas. |
Throughout the construction period |
P |
P |
P |
P |
|
Restrictions
on the height of material/spoil stockpiles. |
P |
P |
P |
P |
||
|
Prompt
hydro-seeding of disturbed areas and cut/fill slopes prior to the permanent
landscaping works. |
P |
P |
P |
P |
||
|
Avoidance
of chunam or shotcreting
slope treatments. |
P |
P |
P |
P |
||
|
Conservation
of topsoil where practical. |
P |
P |
P |
P |
||
|
Site litter
patrols and regular site waste collection. |
P |
P |
P |
▲ |
||
|
Maintenance
of planting. |
P |
P |
P |
P |
||
|
Ecological
Impact |
Minimise
damage outside works areas |
P |
P |
P |
P |
|
|
Construction: |
||||||
|
Material
Storage |
Covers for
dusty stockpiles |
Throughout the construction period |
▲ |
▲ |
▲ |
▲ |
|
Vehicle
movement |
Haul road
watering, vehicle wheel wash prior to exit. Where practical, access roads
should be protected with crushed gravel. |
P |
P |
P |
▲ |
|
|
Plant
maintenance |
All plant
shall be maintained to prevent any undue air emissions. |
P |
P |
P |
P |
|
|
All plant
activity |
Reference
should be made the EM&A Manual Action Plan for measures for consideration
when Noise Limit Levels are not met. |
P |
P |
P |
P |
|
|
Plant
maintenance |
All plant
shall be maintained to prevent any undue noise nuisance. |
P |
P |
P |
P |
|
|
Wheel wash |
All wheel
wash water shall be diverted to a sediment pit. |
Throughout the construction period |
P |
▲ |
▲ |
▲ |
|
Concrete
Truck Washout |
All
concrete trucks shall wash out into a lined pit. |
P |
P |
P |
P |
|
|
Surface
water diversion |
All clean
surface water shall be diverted around the site. |
P |
P |
P |
P |
|
|
Sediment
control |
Sediment
removal facilities shall be provided and be maintained and excavated as
necessary to prevent sedimentation of the channel. Perimeter channels shall
be provided. Works shall be programmed for the dry season where feasible. |
P (Not all, in progress) |
P (Not all, in progress) |
P (Not all, in progress) |
P (Not all, in progress) |
|
|
Fuel can
storage |
All fuel
cans shall be placed within a bundled area.
Any fuel spills shall be mopped up as necessary. |
P |
P |
P |
P |
|
|
Slope
covers |
Finished
slopes and other slopes near drainage areas shall be covered prior to rains to
reduce sedimentation of runoff. Slopes should be hydroseeded
or shotcreted as early as possible to prevent
erosion. |
P |
P |
P |
P |
|
|
Excavation
works |
Excavation
works shall avoid sensitive areas. |
Throughout the excavation work period |
P |
P |
P |
P |
|
Material,
plant movement & fuel can refilling. |
Any fuel or
oil spills shall be excavated and disposed off. |
Throughout the construction period |
P |
P |
P |
P |
|
Generators |
All
generators shall be placed within a bundled area. Any fuel spills shall be mopped up as
necessary. |
P |
P |
P |
P |
|
|
Material
containers |
All empty
bags and containers shall be collected for disposal. |
P |
P |
P |
P |
|
|
Worker
generated litter and Waste |
Litter
receptacles shall be placed around the site.
Litter shall be taken regularly to the refuse collection points. Chemical
toilets (or suitable equivalent) should be provided for workers. Any canteens
should have grease-traps. |
Throughout the construction period |
▲ |
▲ |
▲ |
P |
|
Neighbourhood
nuisance |
All
complaints regarding construction works shall be relayed to the Environmental
Team. |
P |
P |
P |
P |
|
|
Legal requirements |
Different
types of waste should be segregated, stored, transported and disposed of in
accordance with the relevant legislative requirements and guidelines |
P (in progress) |
P (in progress) |
P (in progress) |
P (in progress) |
|
|
On-site separation |
On-site
separation of municipal solid waste and construction/demolition wastes should
be conducted as far as possible in order to minimize the amount of solid
waste to be disposed to landfill. |
P (in progress) |
P (in progress) |
P (in progress) |
P (in progress) |
|
|
Temporary storage area |
Separated
wastes should be stored in different containers, skips, or stockpiles to
enhance reuse or recycling of materials and encourage their proper disposal. |
P |
P |
P |
P |
|
|
Record of wastes |
Records of
quantities of wastes generated, recycled and disposed (with locations) should
be properly kept. |
P (in progress) |
P (in progress) |
P (in progress) |
P (in progress) |
|
|
Trip-ticket
system |
To monitor
the disposal of waste at landfills and control fly-tipping, a “trip-ticket”
system for all solid waste transfer/disposal operations should be
implemented. The system should be included as a contractual requirement, and
monitored by the Environmental Team and audited by the Independent
Environmental Checker. |
P (in progress) |
P (in progress) |
P (in progress) |
P (in progress) |
|
* N/A = Not
Applicable
P = Implemented
▲ =
Rectified