ES 1
An Environmental Permit (EP-085/2000/C) was
granted to Highways Department by the Environmental Protection Department for
the construction of Route 8 Project between Tsing Yi
and Cheung Sha Wan.
This EP covers four phases of the Route 8 Project namely Phase
ES 2
This is the 52nd monthly
Environmental Monitoring and Audit (EM&A) report for “Phase
ES 3
During the monitoring period, some of the major
construction activities undertaken during normal hours are highlighted as
follows:
i.
booster pump house construction;
ii.
excavation;
iii.
traffic diversions;
iv.
utilities diversions and
installation;
v.
bridge deck construction;
vi.
viaduct finishing and surfacing,
vii.
segment delivery, erection and
fixing; and
viii.
deck parapet erection and fixing.
ES 4
During the monitoring period, the major
construction activities undertaken during evening, night time and public holidays
are highlighted as follows:
i.
segment delivery, fixing and
erection; and
ii.
deck parapet erection and fixing.
ES 5
Monitoring of Total Suspended Particulates (TSP)
and Noise were carried out in accordance with the EM&A Manual. Weekly site inspections were conducted by the
ET on 1st, 10th, 17th and 22nd November 2006 and the
joint IEC monthly audit was conducted on
Air Quality
ES 6
A total of 45 sets of
Noise
ES 7
In
order to assess the construction noise impact effectively for all noise
monitoring locations (NSR
Daytime Monitoring
ES 8
A total of 15 sets of Leq(30min)
measurement were taken in the daytime (i.e. 0700 to
Evening-time Monitoring
ES 9
A total of 4 sets of 6 x Leq(5min) measurements were taken in the
evening-time (i.e.
Night-time Monitoring
ES 10
A total of 4 sets of 4 x Leq(5min)
measurements were taken at night-time (i.e. 2300 to 0700 next day) at the
Public-holiday Monitoring
ES 11
A total of 7 sets of 6 x Leq(5min)
measurements were taken in public holidays (i.e. 0700 to
Water Quality
ES 12
A total of 3 Effluent Discharge Licenses were
granted by EPD. In accordance with the
conditions of the licenses, water sampling at designated discharge points shall
be carried out on a monthly basis for area P
ES 13
Eight water samples were taken for the whole
site by CHEC on
ES 14
Three water samples were taken for P1-SA1 (Part
1, Grid
Waste Management
ES 15
A revised Waste Management Plan (Rev. 17) was
submitted to EPD for information on 11th May 2006 with the latest
information including the most up to date estimation of inert C&D materials
and non-inert C&D materials
ES 16
With effect from
ES 17
A total of 209 no. of trucks (approximately 941
m3) of inert C&D materials were delivered to Tuen
Mun Fill Bank during the reporting period. Approximate 115.79 tonnes
of C&D waste was produced on-site and were delivered to SENT. In addition, no chemical waste was disposed
off site during the reporting period.
ES 18
On
Covering of dump trucks delivering dusty
materials off site
ES 19 In order to ensure the covering would be secured and maintained throughout the journey to off-loading destinations, regular training has been provided for frontline staff and reminding notices have been given to all dump truck drivers carrying C&D materials leaving the site. In addition, ad hoc meetings were held between CHEC and their sub-contractors regarding to the rules for transportation of C&D materials to designated disposal locations.
To further strengthen the current trip ticket system, CHEC has
imposed a penalty system for any dump trucks uncovering outside TMA38 with
effect from
Site Audits / Inspections
ES 20 Weekly
site inspections were carried out by the ET and the major findings are
presented below:
|
Item |
Findings |
Corrective and Preventive measures
proposed by CHEC |
Effectiveness of measures |
|
1 |
Open stockpiles of dusty materials were not entirely covered by
tarpaulin sheet at area P1-SA6 (STP). |
All idled open stockpiles (not in operation) have been covered by
impervious sheeting and the remaining stockpiles should be covered by impervious sheeting after operation or
at the end of each working day. |
Completed and |
|
2 |
CHEC was reminded to enhance the dust control measures for the
exposed earth at area P1-SA1 (Part 2, beside abutment E1) during dry season. |
The frequency of water spraying by means of using water bowser and sprinklers has been increased to further
mitigate the dust impact during the dry season. |
Completed and (Please refer Appendix
Q Photo 03). |
|
3 |
No wheel washing facilities were provided at the site exits of area
P1-SA1 (Part 2, Container Port Road West Bound) and at Roundabout CP3/End. |
The vehicular exits at P1-SA1 (Part 2, Container Port Road West
Bound) and at Roundabout CP3/End had been blocked. |
Completed and (Please refer Appendix
Q Photo 04 to 05). |
|
4 |
Petrol interceptor was not properly
functioning at vehicular exit point at area P1-SA1 (Part 2, Pier E16). |
The petrol interceptor has been modified and it was found functioning
properly according to the subsequent site inspection. |
Completed and (Please refer to Appendix Q, Photo 06). |
ES 21
The monthly IEC audit was carried out on
|
Item |
Findings |
Corrective and Preventive measures
proposed by CHEC |
Effectiveness of measures |
|
1 |
The petrol interceptor for wheel washing facilities at vehicular exit
point at area P1-SA1 (Part 2, Pier E16) was not properly functioning. CHEC was reminded to further improve the
petrol interceptor |
The petrol interceptor has been modified and it was found functioning
properly according to the subsequent ET’s site inspection. |
Completed and (Please refer to Appendix Q, Photo 06). |
ES 22
A joint site inspection was carried out with EPD
(Environmental Compliance Division) on
|
Item |
Findings |
Corrective and Preventive measures
proposed by CHEC |
Effectiveness of measures |
|
1 |
All open stockpiles of dusty
material shall be covered entirely by impervious sheeting or to spray with
sufficient water to maintain the entire surface moist, in particular at area
P1-SA1 (Part 2). |
All idled open stockpiles (not in
operation) have been covered by impervious sheeting and the remaining
stockpiles should be covered by
impervious sheeting after operation or at the end of each working day. |
Completed and (Please refer to Appendix Q, Photo 07). |
|
2 |
The frequency of water spraying by
means of using water bowser and sprinklers should
be increased to further mitigate the dust impact generated from the
construction site during dry season |
The frequency of water spraying by
means of using water bowser and sprinklers has been
increased to further mitigate the dust impact during the dry season |
Completed and (Please refer to Appendix Q, Photo 03). |
ES 23
A joint site inspection was carried out amongst EPD
(Environmental Compliance Division and Environmental
Assessment Division), ET, HyD, IEC and CHEC on
Environmental Permits / Licenses
ES 24
The following permits / licenses have been
granted by EPD for the construction of the Phase
i.
Environmental Permit
(EP-085/2000/C)
ii.
Chemical Waste Producer
Registration (WPN – 52
iii.
3 Effluent Discharge Licences
(EP482/269/0038/I; EP482/269/0039/I & EP482/269/0040/I)
iv.
4 Construction Noise Permits.
Environmental Complaints
ES 25
No environmental complaints were received during
the reporting period.
ES 26
A total of
Notifications of Summons and Prosecution
ES 27
Since the commencement of construction, no
notifications of summons nor prosecution were received
on the environmental performance for this Contract.
Future Key Issues
ES 28
The tentative program of major site activities
as well as the impact prediction and control measures for the coming three
months, i.e. December 2006 to February
2007 are summarized below:
|
Construction Works |
Major Impact Prediction |
Control Measures |
|
Utilities installation and
diversions; booster pump house, and bridge deck construction; segment, desk
parapet and noise barrier erection. |
Air impact (dust and machine emission) |
i.
Frequent watering of haul road and
unpaved/exposed areas; ii.
Frequent watering or covering stockpiles with
tarpaulin or similar means; iii.
Regular maintenance of onsite machineries and
vehicles; and iv.
Reinstate the worked area by hydro-seed or
similar means. |
|
|
Water quality impact (muddy run-off) |
i. Collecting
and recycling of wastewater produced on-site if possible; ii.
Perimeter protection such as sandbag barriers
and sealing the bottom of concrete barrier to avoid run-off entering the
existing storm water drainage system; iii.
Diverting the collected effluent to de-silting
facilities for treatment before discharge to public drains; and iv.
Covering of exposed slope with tarpaulin or similar
means during rainstorm |
|
Noise Impact |
i. Scheduling
of noisy construction activities if necessary to avoid persistent noisy
operation; ii.
Controlling the number of plants use on site; iii.
Regular maintenance of machines; and iv.
Use of acoustic barriers if necessary. |