An Environmental
Permit (EP-085/2000/C) was granted to Highways Department by the Environmental
Protection Department for the construction of Route 8 between Tsing Yi and
Cheung Sha Wan Project. This EP covers
four phases of the Route 8 Project namely Phase 1 – Ngong Shuen Chau Viaduct,
Phase 2a – Nam Wan Tunnel and West Tsing Yi Viaduct, Phase 2b – East Tsing Yi
Viaduct and Phase 3 –
This is the 52nd
monthly Environmental Monitoring and Audit (EM&A) report for the “Phase 1 –
Route 8 Ngong Shuen Chau Viaduct (HY/2000/21)” (hereinafter called the “Phase 1
Contract”). This report presents the
results of the EM&A programme conducted during the period between
1.2 Structure of the Report
The structure of the report is as follows:
|
Section 1: |
INTRODUCTION – details the scope and structure of the report. |
|
Section 2: |
PROJECT INFORMATION – summarizes the background and scope of the project, project organization, construction programme and the construction works undertaken during the reporting period. |
|
Section 3: |
ENVIRONMENTAL MONITORING REQUIREMENTS – summarizes the monitoring programmes, Action and Limit Levels, Event Action Plans, environmental mitigation measures as recommended in the EIA Report and relevant environmental requirements. |
|
Section 4: |
IMPLEMENTATION STATUS ON ENVIRONMENTAL PROTECTION REQUIREMENTS – summarizes the implementation of environmental protection measures during the reporting period. |
|
Section 5: |
ENVIRONMENTAL LICENCE AND PERMITTING REQUIREMENTS – summarizes the environmental licences and permits obtained or being applied during the reporting period. |
|
Section 6: |
MONITORING RESULTS – reports the monitoring results obtained in the reporting period. |
|
Section 7: |
AUDIT RESULTS – summarizes the audit findings in the reporting period. |
|
Section 8: |
COMPLAINTS, NOTIFICATIONS OF SUMMONS AND PROSECUTIONS DURING THE REPORTING PERIOD – summarizes the complaints, notifications of summons and prosecutions recorded during the reporting period. |
|
Section 9: |
FUTURE KEY ISSUES – summarizes the future key issues as reviewed from the works programme and work method statements. |
|
Section 10: |