ES 1
An Environmental Permit (EP-085/2000/C) was
granted to Highways Department by the Environmental Protection Department for
the construction of Route 8 Project between Tsing Yi
and Cheung Sha Wan.
This EP covers four phases of the Route 8 Project namely Phase 1 – Ngong Shuen Chau
Viaduct, Phase 2a – Nam Wan Tunnel and West Tsing Yi
Viaduct, Phase 2b – East Tsing Yi Viaduct and Phase 3
–
ES 2
This is the 56th monthly
Environmental Monitoring and Audit (EM&A) report for “Phase 1 - Route 8 Ngong Shuen Chau
Viaduct Contract (HY/2000/21)”. This
report presents the results of the EM&A works conducted during the period
between
ES 3 During the monitoring period, some of the major construction activities undertaken during normal hours are highlighted as follows:
i. booster pump house construction;
ii. excavation;
iii. traffic diversions;
iv. utilities diversions and installation;
v. bridge deck construction;
vi. viaduct finishing and surfacing,
vii. segment delivery, erection and fixing;
viii. deck parapet erection and fixing; and
ix. E&M works
ES 4 During the monitoring period, the major construction activities undertaken during public holidays are highlighted as follows:
i.
Grouting of tendon ducting; and
ii. deck parapet erection and fixing.
ES 5 Monitoring of Total Suspended Particulates (TSP) and Noise were carried out in accordance with the EM&A Manual. Weekly site inspections were conducted by the ET on 9th, 16th and 22nd March 2007 and the joint IEC monthly audit was conducted on 16th March 2007.
Air Quality
ES 6 A total of 36 sets of 1-hour TSP and 15 sets of 24-hour TSP measurement were taken during the reporting period at ASR1, ASR2 and ASR3 and the results of all measurements taken were below the Action/Limit (AL) Levels.
Noise
ES 7
In
order to assess the construction noise impact effectively for all noise
monitoring locations (NSR1 to NSR3) from this Contract, an adjustment approach
was adopted since
Daytime
Monitoring
ES 8 A total of 9 sets of Leq(30min) measurement were taken in the daytime (i.e. 0700 to 1900 hours on normal weekdays) at all monitoring stations (NSR1, NSR2 and NSR3) during the reporting period and no exceedances were recorded.
Evening
and night-time Monitoring
ES 9 Since no construction works were undertaken during evening and night-time, therefore no noise monitoring was carried out for these periods during the reporting month.
Public-holiday
Monitoring
ES 10 A total of 5 set of 6 x Leq(5min) measurements was taken in public holidays (i.e. 0700 to 1900 hours during public holiday) at the three monitoring stations (NSR1, NSR2 and NSR3) during the reporting period and no exceedances were recorded.
Water Quality
ES 11 A total of 3 Effluent Discharge Licenses were granted by EPD. In accordance with the conditions of the licenses, water sampling at designated discharge points shall be carried out on a monthly basis for area P1-SA1 (Part 1) (Grid 1 to 9) and on a quarterly basis for areas P1-SA1 (Part 2) (Grid 10 to 27, Container Port Road E/B), P1-SA6, P1-SA8 and P1-SA11.
ES 12
Five water samples were taken for the whole site
by CHEC on
ES 13
Two water samples were taken for P1-SA1 (Part 1,
Grid 1 to 9) by CHEC on
Waste Management
ES 14 A revised Waste Management Plan (Rev. 17) was submitted to EPD for information on 11th May 2006 with the latest information including the most up to date estimation of inert C&D materials and non-inert C&D materials.
ES 15
With effect from
ES 16 A total of 447 no. of trucks (approximately 2012 m3) of inert C&D materials were delivered to Tuen Mun Fill Bank during the reporting period. Approximate 63.5 tonnes of C&D waste was produced on-site and were delivered to SENT. In addition, no chemical waste was disposed off site during the reporting period.
ES 17
On
Site Audits /
Inspections
ES 18 Weekly
site inspections were carried out by the ET and the major findings are
presented below:
|
Item |
Findings |
Corrective and Preventive measures proposed by CHEC |
Effectiveness of measures |
|
1 |
No drip trays were provided for larvicidal
oil at area P1-SA1 (Part 1, next to vehicular entrance). |
The larvicidal oil has been
removed. |
Completed
and closed. (Please refer to Appendix Q, Photo 01). |
|
2 |
Stagnant water was accumulated at the segment storage yard in area P1-SA1 (Part 1). |
Stagnant water together with deposited silt had been cleared to minimize the risk of mosquito breeding. |
Completed
and closed. (Please refer to Appendix Q, Photo 02). |
|
3 |
Oil stain on the ground was found behind the Kinko’s site office
at area P1-SA1 (Part 2). |
All contaminated
materials had been cleared as chemical waste and temporarily stored at the
chemical waste storage area. |
Completed
and closed. (Please refer to Appendix Q, Photo 03). |
|
4 |
Debris was scattered around the Kinko site office at area P1-SA1. |
All debris and rubbish have been removed. |
Completed
and closed. (Please refer to Appendix Q, Photo 04). |
|
5 |
Open stockpiles of dusty materials were observed at area P1-SA1 (Part 2, near Pier F12). |
All open stockpiles have been removed. |
Completed
and closed. (Please refer to Appendix Q, Photo 05). |
ES 19
The monthly IEC audit was carried out on
|
Item |
Findings |
Corrective and Preventive measures proposed by CHEC |
Effectiveness of measures |
|
1 |
Stagnant water was accumulated at the segment storage yard in area P1-SA1 (Part 1). |
Stagnant water together with deposited silt had been cleared to minimize the risk of mosquito breeding. |
Completed
and closed. (Please refer to Appendix Q, Photo 02). |
|
2 |
Oil stain on the ground was found behind the Kinko’s site
office at area P1-SA1 (Part 2). |
All contaminated
materials had been cleared as chemical waste and temporarily stored at the
chemical waste storage area. |
Completed
and closed. (Please refer to Appendix Q, Photo 03). |
|
3 |
Debris was scattered around the Kinko site office at area P1-SA1. |
All debris and rubbish have been removed. |
Completed
and closed. (Please refer to Appendix Q, Photo 04). |
Environmental
Permits / Licenses
ES 20 The following permits / licenses have been granted by EPD for the construction of the Phase 1 Contract and they are:-
i. Environmental Permit (EP-085/2000/C)
ii. Chemical Waste Producer Registration (WPN – 5213-269-C3215-01)
iii. 3 Effluent Discharge Licences (EP482/269/0038/I; EP482/269/0039/I & EP482/269/0040/I)
iv. 2 Construction Noise Permits.
Environmental
Complaints
ES 21 No environmental complaints were received during the reporting period.
ES 22 A total of 10 environmental complaints had been received for Route 8 - Phase 1 Ngong Shuen Chau Viaduct contract since the commencement of the construction.
Notifications of
Summons and Prosecution
ES 23 Since the commencement of construction, no notifications of summons nor prosecution were received on the environmental performance for this Contract.
Future Key Issues
ES 24 The tentative program of major site activities as well as the impact prediction and control measures for the coming three months, i.e. April 2007 to June 2007 are summarized below:
|
Construction Works |
Major Impact Prediction |
Control Measures |
|
Utilities installation and diversions; booster pump house, and bridge deck construction; parapet and noise barrier erection. |
Air impact (dust and machine emission) |
i. Frequent watering of haul road and unpaved/exposed areas; ii. Frequent watering or covering stockpiles with tarpaulin or similar means; iii. Regular maintenance of onsite machinery and vehicles; and iv. Reinstate the worked area by hydro-seed or similar means. |
|
Water quality impact (muddy run-off) |
i. Collecting and recycling of wastewater produced on-site if possible; ii. Perimeter protection such as sandbag barriers and sealing the bottom of concrete barrier to avoid run-off entering the existing storm water drainage system; iii. Diverting the collected effluent to de-silting facilities for treatment before discharge to public drains; and iv. Covering of exposed slope with tarpaulin or similar means during rainstorm |
|
|
Noise Impact |
i. Scheduling of noisy construction activities if necessary to avoid persistent noisy operation; ii. Controlling the number of plants use on site; iii. Regular maintenance of machines; and iv. Use of acoustic barriers if necessary. |