8 ENVIRONMENTAL NON-COMPLIANCE, COMPLAINTS, NOTIFICATIONS OF SUMMONS AND PROSECUTION
8.1 Summary of Environmental Non-Compliance
8.1.1
No
Action / Limit Level exceedances were recorded in this reporting period
and they are summarized in Table 8.
Table 8.
|
Media/ Nature |
No. of
Exceedance |
Action
Taken |
Results
of Action Taken |
Remarks |
||
|
Action
Level |
Limit
Level |
|||||
|
Air Quality |
|
0 |
0 |
- |
- |
- |
|
24-hour TSP |
0 |
0 |
- |
- |
- |
|
|
Media/ Nature |
No. of
Exceedance |
Action
Taken |
Results
of Action Taken |
Remarks |
||
|
Noise |
Day Time |
0 |
0 |
- |
- |
- |
|
Evening Time |
0 |
0 |
- |
- |
- |
|
|
Night Time |
0 |
0 |
- |
- |
- |
|
|
Public
|
0 |
0 |
- |
- |
- |
|
8.2.1
One environmental related complaint was received
by Environmental Protection Department (EPD) and subsequently referred to R8-ET
on
8.2.2 An independent complaint investigation was carried out by R8-ET on 25th June 2007, followed by a joint site inspection together with the RSS and CHEC on 26th June 2007, it was found that the area concerned did not generate any dust nuisance and furthermore, a water bower was observed being deployed by CHEC as a dust suppression measure for P1-SA1 (G.L. 0 to 8).
Site inspection was carried out by R8T-ET and
RSS on a daily basis and dust suppression measures for the whole site area was
carried out by CHEC. Thus, any dust
nuisance were generated, then R8T-ET, RSS and CHEC would have been addressed /
rectified in the first instance. A water bower provided by CHEC has been used
as a dust suppression measure at a frequency of at least 3 times a day (once in
the morning and twice in the afternoon) and obviously if the area was found too
dry by any on-site staff, the frequency of water spraying would be increased
accordingly.
Furthermore,
part of the area P1-SA1 (Grid line 0 to 8) was handed over to another
Contractor (MHYHJV) for the construction of Route 8 – Stonecutters Bridge
Contract (SCB) on
To conclude, the current dust suppression measures provided by CHEC at the area concerned was acceptable and thus no further action was required at this stage.
8.2.1 The summary for all environmental complaints received since the commencement of the Contract is presented in Table 8.2. The details of previous complaints and statistics are attached in Appendices O1 and O2 respectively.
Table 8.2 Summary of Total Complaint Received
|
Total No.
of Complaint Received |
No. of
complaint received within reporting period |
No. of
Active Complaint |
No. of
Inactive/Closed Complaint |
|
11 |
1 |
0 |
11 |
8.3 Summary of Notifications of Summons and Prosecution
8.3.1 No notifications of summons or prosecution were received regarding the non-compliance of the environmental performance for this Contract since the commencement of construction.